Module Managers/Key Users 5/16/08 Meeting Notes

& Team-EX Meetings.

About twenty Module Managers and Key Users met for 45 minutes on Friday afternoon (5/16) to receive updates on the EX Implementation project. The week of May 12 was an important milestone because the First Data Conversion Pass was begun during the week. Notes from the meeting can be found here.

Internet Explorer 7: Update

& Software installs & updates.

Since the IE7 update, some users across campus have had the computer “hang” shortly after logging into Novell. This issues is currently being looked into. For the time being, IE7 is NOT being pushed to computers that haven’t had the update until this issues has been resolved. To cope with the issue, when users eventually… Read more »

May 12 Milestone Day: First Pass Data Conversion

& General.

Today, May 12, is another big “milestone” day in our EX Implementation Project. Thanks to the hard work of a lot of people, Becky Brenneman, conversion programmer at Jenzabar, is launching the First Pass Data Conversion process today — a process that will continue all week. Here are several things we want everyone to be… Read more »